Effect Of Delays In The Rusun Ujung Menteng House Project On The Progress Of Time

Main Article Content

Muhamad Sobirin , Prasetyadhie , Naniek Widayati Priyomarsono , Alfred Jonathan Susilo

Abstract

The work of the East Canal Flood Rusun Project (BKT) Ujung Menteng East Jakarta experienced delays that should
have been dated December 22, 2021, in fact not achieved, many things were a factor in the delay in this project.
The purpose in this study is to want to know what factors have to do with the delay in the construction of the
Ujung Menteng Flats Project. As well as what factors have an effect in the delay to the construction work of the
Ujung Menteng Flats project. The determining factors in the overlongness are the Factor of Emigrant value t
calculated by 2,242 > 2,014, with a significant .030 < 0.05, the Cost Factor of the calculated value of 10,113>
2,014, with significant at .000 < 0.05, the Labor Factor has a calculated value of 5,895> 2,014, with a significant
amount of 000 < 0.05, the Weather Factor has a t value of 4,598> 2,014, with a significant amount of 000 < 0.05.
The Tool Factor has a t value of 7,861 with a significant of 000 < 0.05. Factor Management has a t value of 4,913
>2,014, with a significant amount of 000 < 0.05.